COLDSTREAM SITE CUT & POOL EXCAVATION

A site cut and a pool dig on the one block in Coldstream, May 2021. 130 cubic metres of material went out the gate.

// The Job

ONE BLOCK, 130 M³ OUT THE GATE

We did the site cut and dug the pool on the same Coldstream block, and 130 cubic metres of material went out the gate. If there's a pool going in with your build or a big backyard job, book the dig with the site cut, not after it. Pool digs and dams have their own page now, with a dam job from Warburton.

The photos tell most of it. A levelled clay pad with the laser set up on it, the pool hole itself, and a Yanmar loading a tipper parked right up beside it.

Suburb
Coldstream
Material Out
130 cubic metres
Scope
Site cut and pool dig
When
May 2021
  • Site cut and pool excavation done on the one block
  • 130 cubic metres of material carted out the gate
  • A rotating laser set up on site for the levels
  • Dark topsoil sitting over yellow clay in the cut faces

Posted from site, 12 May 2021. See the original on our Instagram

Yellow mini excavator on a levelled clay pad at the Coldstream job, a red rotating laser on the pad and paddocks beyond the back fence
The pool hole at the Coldstream job, a flat pale floor at the bottom and a red rotating laser sitting on its case at the edge
// Two Digs, One Visit

WHY THE POOL GOES IN WITH THE SITE CUT

Dig the pool on its own later and the machine comes back, the trucks come back, and somebody sets the levels up all over again. Do it with the site cut and it's one setup.

Levels are the bit people don't think about. The finished pool edge has to sit right against the house floor, the paving, and the fall that takes water away from both. When the pad and the pool hole come off the same laser on the same visit, they're measured from the same point. That's ours in the photo, sitting on its case at the edge of the hole.

Then there's the dirt. A pool hole throws out a lot of material for its size and it all comes out at once. If the site cut's happening at the same time you're paying for one run of trucks, not two. On this one, 130 cubic metres went out the gate.

What we don't decide is the shape. The hole gets dug to your pool builder's set out and drawings, so we want those in hand before the day. There's one more reason to line the two jobs up. Victoria's building regulator says pool work has to be finished within six months of starting, unless other building work is going on at the same property, in which case it can run on the same time frame as that work.

// Where It Went

130 CUBIC METRES, AND WHERE IT GOES NOW

Out the gate is the simplest version of a pool dig. It's also the part where the rules have moved most since we did this job.

We dug this one in May 2021. Victoria's new environment protection laws came in on 1 July 2021, and the waste soil rules that apply today came with them. EPA Victoria now wants soil identified and classified before anyone hands it over to be carted away. Clean soil, which EPA calls fill material, has to go somewhere that's authorised to take it. It can't just go to whoever's filling a hole down the road.

That's why we ask what your block's been used for before a load leaves it. This one backs onto paddocks. On a block like that it's worth knowing what's been on the land.

Volume catches people out too. Dirt takes up more room dug than it did in the ground, and clay more than most. We've broken that down on the Silvan job, where 650 cubic metres came out and none of it left the property. The 2.5 metre cut in Healesville is the other extreme, 17 loads out with no room to move. For the bigger picture on cuts, see our site cuts page.

Yanmar mini excavator loading a tipper at the Coldstream job, with dug soil heaped across the levelled pad in front
Straight sided dig through dark topsoil into yellow clay at the Coldstream job, a long level laid across the top edge
// The Pool Paperwork

WHAT HAPPENS EITHER SIDE OF THE DIG

The dig's the quick part. The paperwork runs both sides of it, and most of it lands on the owner.

Before. You need a building permit before a pool, spa or safety barrier goes in, unless the work is exempt, and it's issued by a registered building surveyor. Once it's issued, work has to start within 12 months.

While the hole's open. The Building and Plumbing Commission, the state's building regulator, puts it plainly: it's the owner's responsibility to make sure a compliant barrier is in place around the pool. A compliant temporary fence is one way to do that. Have it sorted for the day the hole opens up.

After. Any pool or spa that can hold more than 30cm of water has to be registered with council, and around here that's Yarra Ranges Council. For a new permanent pool that's within 30 days of the occupancy permit or certificate of final inspection. Then a certificate of barrier compliance gets lodged, and a fresh one every four years after that.

None of that's ours to sign off. We'd just rather you hear it before the machine turns up than after.

// Before You Start

WHAT WE'D CHECK ON YOUR COLDSTREAM BLOCK

Planning a pool with a new build or a big backyard job around Coldstream? Here's what we'd want sorted before anyone books machine time.

Start with what's under the lawn. Lodge a Before You Dig Australia enquiry, it's free. Just know what it won't tell you. BYDA's own FAQ says domestic services don't typically show up on the plans, and anything put in privately, like irrigation or power run out to a shed, won't be there at all. A backyard is exactly where a pool goes, so walk us round and show us where your stormwater, sewer and any shed power actually run.

Then access. The machine and the trucks both have to get to the back. On this job the tipper came in right beside the excavator. On a tighter block the truck sits on the street and everything gets carried out to it, which is slower and costs more machine time.

And timing. Spring ground across the valley is still carrying the winter wet, and clay like the yellow stuff in our photos is heavy and sticky to dig and cart when it's wet. Plenty of people want a pool in the ground before summer. Get the permit moving first, then book the dig early.

Permit Before The Hole

A pool, spa or safety barrier needs a building permit before it goes in unless it's exempt. Get a building surveyor on board before you book the dig.

Fence The Open Hole

Keeping a compliant barrier around the pool is the owner's job. A compliant temporary fence is one way to meet it while the pool's being built.

Your Pipes Aren't On The Plans

Before You Dig shows network services. Private stormwater, irrigation and shed power usually won't be on there, so show us where they run.

// FAQ

POOL DIG & SITE CUT QUESTIONS

The questions we get asked most when a pool goes in with a site cut, around Coldstream and the wider Yarra Valley.

Can the site cut and the pool dig be done in the same visit?

Yes. On this Coldstream job both came out of the one block. Doing them together means one machine setup, one set of levels off the same laser, and one run of trucks for the spoil instead of two. The pool hole still gets dug to your pool builder's set out, so we need their drawings before the day.

Do I need a building permit before the pool hole is dug?

In Victoria you need a building permit before installing a pool, spa or safety barrier unless the work is exempt, and it comes from a registered building surveyor. Once it's issued, the work has to start within 12 months. Get the permit moving before you book the dig.

Who has to fence the pool while it's being built?

The owner. The Building and Plumbing Commission puts the responsibility for a compliant barrier around the pool on the owner, and a compliant temporary fence is one way to meet it. Have it sorted for the day the hole is open, not after.

When does a new pool have to be registered with council?

Any pool or spa that can hold more than 30cm of water has to be registered. For a new permanent pool that's within 30 days of the occupancy permit or certificate of final inspection being issued. Around Coldstream that's Yarra Ranges Council.

How often does the pool barrier have to be certified?

After the first certificate of barrier compliance, a new one has to be lodged with council every four years. A certificate is only valid for 30 days after it's issued, so it has to reach council inside that window.

Will Before You Dig show the pipes in my backyard?

Probably not. Lodging an enquiry is free and you should do it, but Before You Dig Australia's own FAQ says domestic services don't typically appear on the plans, and privately installed ones like irrigation or power run to a shed won't be there. Show us where your stormwater, sewer and shed power run before we start.